01 · The challengeRepairing the retained barn structure
The existing structure was in poor condition and required extensive repair while new elements were built around the retained frame. Difficult ground conditions called for a floating reinforced-concrete slab and deep strip foundations. Green-belt constraints and nearby archaeological interest added further planning and delivery considerations.
02 · The responseCoordinating foundations and heritage fabric
The team coordinated the retained fabric, foundations, structure and new envelope as one buildable sequence. Early decisions focused on protecting original elements, resolving interfaces between old and new work and keeping information moving between the client, consultants, suppliers and site team.
03 · The resultSeven holiday apartments, with character retained
The completed scheme combines a full curtain-wall front elevation with retained A-frames, roof features, flint walls and brick flooring. Landscaping was designed to sit comfortably within the green-belt context, creating seven distinctive apartments from a structurally demanding starting point.